Corporate Incompetence: Officials say nuclear disaster could have been avoided!

16 September 2011, the Japan Atomic Energy Agency says the disaster at Fukushima Daiichi nuclear plant could have been avoided.

They say if water injection began four hours sooner there would have been no melt downs.

Anyone who’s been following the situation from day one knows that Tokyo Electric Power Company has dragged their feet on just about everything connected to dealing with the disaster.  Especially at the beginning when it seemed that TEPCo officials just refused to believe that anything was wrong!

Of the plant’s six reactors, reactors 1 and 3 suffered meltdowns after losing cooling functions.

Reactor 2 suffered a hydrogen explosion on 15 March, which caused the release and spread of massive amounts of radioactive isotopes.